Line 14: Line 14:
  
 
== Agenda ==
 
== Agenda ==
 +
 +
* CDFG R&D Testing: (TBC: Adam Anderson: 10-min)
 +
** Requirements and scope of testing needed.
 +
** Testing requirements:
 +
https://docs.google.com/document/d/1n9Wdjds6iPtWdnnmdQNeIaI80c8aMzTKvlcmMpWvvjI/edit?usp=sharing
 +
 +
* R&D and Prototype Testbeds (Brad Benson: 10-min)
 +
** Testbed plan, scope, and schedule
 +
** Relationship with readout down-select
 +
** Test equipment needs: cold-loads, choppers, lenses, c
 +
 +
* Optics Tube Testing (Katie Harrington: 15-min)
 +
** Optics tube testing needs.
 +
** Balance of warm and cold testings.
 +
** Integrated testing with detectors. 
 +
** Lessons learned from SO.
 +
 +
* Long-term testing plan through production (Brad Benson: 20-min)
 +
** Prototype detector testbeds
 +
** Optics tube testers: Dedicated LAT optics tube testers, SAT cryostats
 +
** Production test cryostats
 +
** Test equipment needs
 +
** Coordination with readout testbeds
 +
** Plan ahead of August Review and ahead of CD-1
  
 
== Notes ==
 
== Notes ==
 +
 +
https://docs.google.com/document/d/1spg9OyGyyx7FBVgSBRuSI-O2Ns_ayYIol8yr9Iltfqo/edit?usp=sharing

Revision as of 20:57, 26 March 2020

Link back to main meeting page:

Zoom link: https://lbnl.zoom.us/j/411685173

Charge

  • Present an overall testing plan
    • 1st, for 2020/2021 prototype wafers,
    • Longer term plans (should include optics tube testing)
    • Are any setups doing both readout and detector testing, or is it going to be all separate? Present/develop plan for getting enough capacity, and uniformity/consistency of testing setups.
  • Plan schedule of design reviews for these subsystems needed before CD1

Agenda

  • CDFG R&D Testing: (TBC: Adam Anderson: 10-min)
    • Requirements and scope of testing needed.
    • Testing requirements:

https://docs.google.com/document/d/1n9Wdjds6iPtWdnnmdQNeIaI80c8aMzTKvlcmMpWvvjI/edit?usp=sharing

  • R&D and Prototype Testbeds (Brad Benson: 10-min)
    • Testbed plan, scope, and schedule
    • Relationship with readout down-select
    • Test equipment needs: cold-loads, choppers, lenses, c
  • Optics Tube Testing (Katie Harrington: 15-min)
    • Optics tube testing needs.
    • Balance of warm and cold testings.
    • Integrated testing with detectors.
    • Lessons learned from SO.
  • Long-term testing plan through production (Brad Benson: 20-min)
    • Prototype detector testbeds
    • Optics tube testers: Dedicated LAT optics tube testers, SAT cryostats
    • Production test cryostats
    • Test equipment needs
    • Coordination with readout testbeds
    • Plan ahead of August Review and ahead of CD-1

Notes

https://docs.google.com/document/d/1spg9OyGyyx7FBVgSBRuSI-O2Ns_ayYIol8yr9Iltfqo/edit?usp=sharing